Displaying results 1-11 out of 11 total.Task Id | Task Summary | Status | Start Date | End Date | Percent Complete | |
---|---|---|---|---|---|---|
737 | Obtencion de Local | Open | 2010-03-25 14:00 | * 2010-04-30 13:00 | 0% | |
738 | Acondicionamiento | Open | 2010-05-01 13:00 | * 2010-07-15 13:00 | 0% | |
739 | Adquisición de Hardware | Open | 2010-07-15 13:00 | * 2010-08-07 13:00 | 0% | |
740 | Instalación de equipos y redes | Open | 2010-08-07 13:00 | * 2010-08-17 13:00 | 0% | |
741 | Instalación de Servicios | Open | 2010-08-07 13:00 | * 2010-08-17 13:00 | 0% | |
742 | Propaganda | Open | 2010-08-14 13:00 | * 2010-08-17 13:00 | 0% | |
743 | Apertura | Open | 2010-08-17 13:00 | * 2010-08-17 13:00 | 0% | |
744 | Busqueda | Open | 2010-03-25 14:15 | * 2010-04-17 00:00 | 0% | |
745 | Recurso Financiero | Open | 2010-04-17 00:00 | * 2010-04-23 21:00 | 0% | |
746 | Tramite/Adquisicion del local | Open | 2010-04-23 21:00 | * 2010-04-30 21:00 | 0% | |
747 | C.- Planeacion/Diseño de la Estructura | Open | 2010-05-01 13:15 | * 2010-05-09 01:00 | 0% |